Concurrent Delay Revisited Adyard Abu Dhabi v SD Marine Services (Article 7)

  1. In 2010 we saw the landmark decision in City Inn v Shepherd which was much commented upon, mainly because the judges apportioned delays for extensions of time. It was suggested that although this was a Scottish case it would be used as guidance by the English courts.

  2. However many considered that the position in City Inn v Shepherd was not the position in English law and a recent case supports that view.

  3. Adyard Abu Dhabi v SD Marine Services [2011] was heard in the Commercial Courts, not the TCC. The judgement is still, of course, of great importance.  The case concerned the procurement of ships and centred around the method of measurement of delay where both buyer and contractor had caused delays.  The situation where both contracting parties have potentially caused a delay is all too familiar and therefore highly relevant in the construction industry.

  4. The contractor claimed that variations to the contract given shortly before the original unamended contract completion date resulted in a delay.

  5. It was claimed that further time was required to complete the variations and that this resulted in a completion date which was beyond the original contractual completion date. In simple terms the contractor claimed that it was entitled to the difference between the original and the actual completion date as a result of the variations.

  6. The courts said that this method is entirely theoretical and that it did not demonstrate whether the variations did, in fact, delay the project.

  7. The most appropriate method of establishing entitlement to the delays is to consider as a matter of fact whether or not the alleged delays did affect the completion date. This means that the actual progress of the works has to be taken into account and the delaying event must affect completion which ordinarily will mean that it should fall on the critical path.

  8. Adyard’s argument that its approach, that is by just considering the variations (design changes) in isolation was the correct approach regardless of what other events might have been delaying the works and regardless of whether the variation would have any impact on actual progress. The judge disagreed saying that it was wrong both in principle, was not in accord with the authorities and was contra to common sense. The judge specifically said that City Inn did not reflect English law.

  1. The judge in this case found that as a matter of fact the project was already in critical delay well before the design changes occurred and that Adyard was not entitled to additional time simply because the events did not actually cause delay. He said that concurrent delay is

“a period of project overrun which is caused by two or more effective causes of delay which are of approximately equal causative potency”.

This case again illustrates the difficulties with concurrent delay and follows the case of DeBeers v Atos [2010] which also supports the position that apportionment of concurrent delay is not appropriate in English law.

  1. The measure of any entitlement to revise the completion date is then the period of time between the planned completion date as a result of the delay and the planned completion date at the time of the delay occurring but without considering the effect of the delay.

  2. The resulting period of time is then added to the original completion date, not to the planned completion without the delay.

  3. If no programmes are available to establish the planned completion date at the time of the delay then the likely completion date, with and without the effect of the delay considered, would have to be assessed by other means such as consideration of the outstanding amount of work based on a contract or as planned programme or failing that contemporaneous records or common sense.

 


  • Sheffield

    The Annexe,
    260 Ecclesall Road South,
    Ecclesall,
    Sheffield,
    S11 9PS

    Tel - 0114 230 1329

  • London

    Adam House,
    7-10 Adam Street,
    London,
    WC2N 6AA

    Tel – 020 7520 9295

  • Leeds

    Suite 69,
    4100 Park Approach,
    Thorpe Park,
    Leeds,
    LS15 8GB

    Tel - 0113 397 0358

  • Warrington

    Suite 41,
    Lakeview 600,
    Lakeside Drive,
    Centre Park Square,
    Warrington,
    WA1 1RW

    Tel - 01925 984705

  • Manchester

    3 Hardman Street,
    Manchester,
    M3 3HF

    Tel - 0114 230 1329

  • Birmingham

    Birmingham Business Park,
    4200 Waterside Centre,
    Solihull Parkway,
    Birmingham,
    B37 7YN

    Tel - 0121 481 2381

  • Liverpool

    Horton House,
    Exchange Flags,
    Liverpool,
    L2 3PF

    Tel - 07753 837149