Back to Basics #42 - NEC Programme Acceptance (Part 2) – Helpful Timeline Diagrams

NEC Programme Acceptance (Part 2) – Helpful Timeline Diagrams – Back to Basics #42

Securing Programme Acceptance under NEC3

In our last issue we looked at the preparation of the submission of the Accepted Programme under the NEC 3 Contract and importantly what needs to be included within the Programme being issued for Acceptance.

This time we will look at the process of Acceptance and look at the reasons a Project Manager can reject the Programme. Next time we will look at revising and updating the Programme.

b2b_42.png
NEC Programme Acceptance (Part 2)

Our Team of Experts can help you understand your Contract obligations and prepare a fully compliant NEC Programme. 

  • Sheffield

    The Annexe,
    260 Ecclesall Road South,
    Ecclesall,
    Sheffield,
    S11 9PS

    Tel - 0114 230 1329

  • London

    Adam House,
    7-10 Adam Street,
    London,
    WC2N 6AA

    Tel – 020 7520 9295

  • Leeds

    Suite 69,
    4100 Park Approach,
    Thorpe Park,
    Leeds,
    LS15 8GB

    Tel - 0113 397 0358

  • Warrington

    Suite 41,
    Lakeview 600,
    Lakeside Drive,
    Centre Park Square,
    Warrington,
    WA1 1RW

    Tel - 01925 984705

  • Manchester

    3 Hardman Street,
    Manchester,
    M3 3HF

    Tel - 0114 230 1329

  • Birmingham

    Birmingham Business Park,
    4200 Waterside Centre,
    Solihull Parkway,
    Birmingham,
    B37 7YN

    Tel - 0121 481 2381

  • Liverpool

    Horton House,
    Exchange Flags,
    Liverpool,
    L2 3PF

    Tel - 07753 837149