Adjudication Process – Helpful Timeline Diagram – Back to Basics #40
The Adjudication Timeline
Continuing on from our Back to Basics Series on Helpful Timelines, this mailshot focusses on the timeline surrounding Adjudication.
The diagram below represents a simplified version of the timeline surrounding Adjudication:
Under the ''Construction Act'' and Scheme for Construction Contracts any party can commence an Adjudication at any time, providing that a dispute has crystallised.
The Adjudicator is to reach their decision within 28 days, following the service of the Notice of Intention to Adjudicate. This can be extended by 14 days with the consent of the Referring Party, any further extension must be agreed by both parties.
For a detailed guide on Adjudication please refer to the Ramskill Martin Article dated 01 July 2022 which can be found by clicking HERE
If you need assistance with any matters involving Adjudication, Ramskill Martin’s Team of Consultants can assist you.
-
Sheffield
The Annexe,
260 Ecclesall Road South,
Ecclesall,
Sheffield,
S11 9PSTel - 0114 230 1329
-
London
Adam House,
7-10 Adam Street,
London,
WC2N 6AATel – 020 7520 9295
-
Leeds
Suite 69,
4100 Park Approach,
Thorpe Park,
Leeds,
LS15 8GBTel - 0113 397 0358
-
Warrington
Suite 41,
Lakeview 600,
Lakeside Drive,
Centre Park Square,
Warrington,
WA1 1RWTel - 01925 984705