Back to Basics #39 - JCT D&B 2016 – Helpful Timeline Diagrams

JCT D&B 2016 – Helpful Timeline Diagrams – Back to Basics #39

Interim Payment Timelines under JCT

Continuing our Back to Basics Series on payment timelines under different forms of Contract, today’s diagrams are for the Interim Payment under the JCT Design & Build (DB) Contract.

The diagram below represents, in a simplified way, the Interim Payment Timeline under the JCT Design & Build 2016 Contract:

39.1.jpg

The JCT Design and Build Contract specifies a period of 14 days from the Due Date to the Final Date for Payment. Alongside specifying the general period applicable to Interim Payment, the Contract also specifies the timescales applicable for the issuing of Payment Notices and Pay Less Notices. It is important that parties are aware of these periods, as failure to issue the relevant Notice in time could result in the Employer being obliged to pay the sum stated in the Contractor’s Interim Application.

The diagram below shows more detail of the steps and periods applicable to Interim Payments under the JCT Design and Build 2016 Contract and identifies the dates that the relevant Notices need to be issued:

39.2.jpg

If you need assistance with anything involving payment under a JCT form of Contract or any matter associated with this suite of Contracts, Ramskill Martin’s team of consultants can assist you, whether the issue is related to the Contract, Commercial matters or Programming / Time.

  • Sheffield

    The Annexe,
    260 Ecclesall Road South,
    Ecclesall,
    Sheffield,
    S11 9PS

    Tel - 0114 230 1329

  • London

    Adam House,
    7-10 Adam Street,
    London,
    WC2N 6AA

    Tel – 020 7520 9295

  • Leeds

    Suite 69,
    4100 Park Approach,
    Thorpe Park,
    Leeds,
    LS15 8GB

    Tel - 0113 397 0358

  • Warrington

    Suite 41,
    Lakeview 600,
    Lakeside Drive,
    Centre Park Square,
    Warrington,
    WA1 1RW

    Tel - 01925 984705