Back to Basics #35 - NEC 3 – Helpful Timeline Diagrams

Back to Basics #35 - NEC 3 – Helpful Timeline Diagrams  

CE Quotation Timelines under NEC

As mentioned last time, as part of our Back to Basics series, we have provided you with some useful diagrams that we have prepared to help you understand various contract timelines.

These can be printed off (if you are old school) or saved to your computer to act as a useful aide memoire which we hope you find useful.

Today’s diagram is for the Compensation Event Quotation Timeline under NEC3.

 

Below is the Timeline for the NEC3 Engineering and Construction Contract MAIN CONTRACT:

b2b35img1.jpg

 

The Sub-Contract is a similar process BUT the durations are amended to ensure that the Main Contract can fulfil its obligations.

Below is the SUB-CONTRACT Timeline:

b2b_35_img_2.jpg

  • Sheffield (Head Office)

    The Annexe
    260 Ecclesall Road South
    Ecclesall
    Sheffield
    S11 9PS
    
    Tel – 0114 230 1329
    
    
  • London

    Adam House
    7-10 Adam Street
    London
    WC2N 6AA
    
    Tel – 020 7520 9295
    
    
  • Liverpool

    Horton House
    Exchange Flags
    Liverpool
    L2 3PF
    
    Tel- 0114 230 1329
    
  • Manchester

    3 Hardman Street
    Manchester
    M3 3HF
    
    Tel – 0114 230 1329
    
    
  • Birmingham

    Birmingham Business Park
    4200 Waterside Centre
    Solihull Parkway
    Birmingham
    B37 7YN
    
    Tel – 0121 481 2381