Back to Basics #35 - NEC 3 – Helpful Timeline Diagrams

Back to Basics #35 - NEC 3 – Helpful Timeline Diagrams  

CE Quotation Timelines under NEC

As mentioned last time, as part of our Back to Basics series, we have provided you with some useful diagrams that we have prepared to help you understand various contract timelines.

These can be printed off (if you are old school) or saved to your computer to act as a useful aide memoire which we hope you find useful.

Today’s diagram is for the Compensation Event Quotation Timeline under NEC3.

 

Below is the Timeline for the NEC3 Engineering and Construction Contract MAIN CONTRACT:

b2b35img1.jpg

 

The Sub-Contract is a similar process BUT the durations are amended to ensure that the Main Contract can fulfil its obligations.

Below is the SUB-CONTRACT Timeline:

b2b_35_img_2.jpg

  • Sheffield

    The Annexe,
    260 Ecclesall Road South,
    Ecclesall,
    Sheffield,
    S11 9PS

    Tel - 0114 230 1329

  • London

    Adam House,
    7-10 Adam Street,
    London,
    WC2N 6AA

    Tel – 020 7520 9295

  • Leeds

    Suite 69,
    4100 Park Approach,
    Thorpe Park,
    Leeds,
    LS15 8GB

    Tel - 0113 397 0358

  • Warrington

    Suite 41,
    Lakeview 600,
    Lakeside Drive,
    Centre Park Square,
    Warrington,
    WA1 1RW

    Tel - 01925 984705

  • Manchester

    3 Hardman Street,
    Manchester,
    M3 3HF

    Tel - 0114 230 1329

  • Birmingham

    Birmingham Business Park,
    4200 Waterside Centre,
    Solihull Parkway,
    Birmingham,
    B37 7YN

    Tel - 0121 481 2381

  • Liverpool

    Horton House,
    Exchange Flags,
    Liverpool,
    L2 3PF

    Tel - 07753 837149