Back to Basics #34 - NEC 3 – Helpful Timeline Diagrams

NEC 3 – Helpful Timeline Diagrams – Back to Basics #34

Over the next few weeks, as part of our Back to Basics series, we thought that we would provide you with some useful diagrams. We have prepared these to help you understand various contract timelines.

These can be printed off (if you are old school) or saved to your computer to act as a useful aide memoire.

Today’s diagrams are for the Compensation Event Notification Timeline under NEC3.

 

Below is the Timeline for the MAIN CONTRACT:

b2b34_img_1.jpg

 

The Sub-Contract is a similar process BUT the durations are slightly reduced to ensure that the Main Contract can fulfil its obligations.

 

Below is the Sub-Contract Timeline:

b2b34_img_2.jpg

 

If you need assistance with anything involving Compensation Events under NEC 3 or 4 or any matter associated with these contracts, Ramskill Martin’s Team of Consultants can assist you, whether the time is related to Contract, Commercial or Programming / Time.

 

 

  • Sheffield (Head Office)

    The Annexe
    260 Ecclesall Road South
    Ecclesall
    Sheffield
    S11 9PS
    
    Tel – 0114 230 1329
    
    
  • London

    Adam House
    7-10 Adam Street
    London
    WC2N 6AA
    
    Tel – 020 7520 9295
    
    
  • Liverpool

    Horton House
    Exchange Flags
    Liverpool
    L2 3PF
    
    Tel- 0114 230 1329
    
  • Manchester

    3 Hardman Street
    Manchester
    M3 3HF
    
    Tel – 0114 230 1329
    
    
  • Birmingham

    Birmingham Business Park
    4200 Waterside Centre
    Solihull Parkway
    Birmingham
    B37 7YN
    
    Tel – 0121 481 2381