Back to Basics #36 - JCT D&B 2011 – Helpful Timeline Diagrams

JCT D&B 2011 – Helpful Timeline Diagrams – Back to Basics #36

Interim Payment Timelines Under JCT

Continuing our Back to Basics Series on payment timelines under different forms of contract, today’s diagrams are for the Interim Payment under the JCT Design & Build (DB) Contract. We still see many clients using the 2011 version of the JCT Contracts, so in this review we look into the Interim Payment Timeline of the 2011 version and we will review the 2016 version separately in the series.

 

The diagram below represents a simplified version of the Interim Payment Timeline under the JCT Design & Build 2011 Contract:

JCTDB_Slide_1.jpg

 

The JCT Design and Build Contract specifies a period of 14 days from the Due Date to the Final Date for Payment. Alongside specifying the general period applicable to Interim Payment, the Contract also specifies the timescales applicable for the issuing of Payment Notices and Pay Less Notices. It is important that parties are aware of these periods, as failure to issue the relevant notice in time could result in the Employer being obliged to pay the sum stated in the Contractor’s interim application.

 

The diagram below shows more detail of the steps and periods applicable to Interim Payments under the JCT Design and Build 2011 Contract  and identifies the dates that the relevant notices need to be issued:

JCTDB_Slide_2_(2)_2.jpg

 

If you need assistance with anything involving payment under a JCT form of contract or any matter associated with this suite of contracts, Ramskill Martin’s Team of Consultants can assist you, whether the issue is related to the Contract, Commercial matters or Programming / Time.

 

  • Sheffield (Head Office)

    The Annexe
    260 Ecclesall Road South
    Ecclesall
    Sheffield
    S11 9PS
    
    Tel – 0114 230 1329
    
    
  • London

    Adam House
    7-10 Adam Street
    London
    WC2N 6AA
    
    Tel – 020 7520 9295
    
    
  • Liverpool

    Horton House
    Exchange Flags
    Liverpool
    L2 3PF
    
    Tel- 0114 230 1329
    
  • Manchester

    3 Hardman Street
    Manchester
    M3 3HF
    
    Tel – 0114 230 1329
    
    
  • Birmingham

    Birmingham Business Park
    4200 Waterside Centre
    Solihull Parkway
    Birmingham
    B37 7YN
    
    Tel – 0121 481 2381